EVENT
|
DATE*
|
|
Issuance of RFP
|
2/10/2012
|
|
Proposers Conference - At the Marshall Depot
|
2/29/2012, at 1:30pm
|
|
Questions Deadline - It is the proposer’s sole responsibility to review this web site and retrieve all documents prior to the RFP due date.
|
3/6/2012 at 2:00 pm
|
|
Proposals Due
|
3/15/2012 by 4:00 pm CST)
|
|
RFP Evaluation Team meeting to review and rank proposals
|
3/16/2012 – 3/21/2012
|
|
Notification of tentative Contract Award (contingent upon Executive Committee approval)
|
3/22/2012, or as soon thereafter as practical
|
|
Contract Negotiations
|
3/26/2012 – till completed
|
|
Executive Committee Approval
|
4/5/2012
|
|
Notification of Contract Award
|
4/5/2012, or as soon thereafter as practical
|
|
CONSTRUCTION BEGINS
|
4/23/2012, or as soon thereafter as practical
|
|
Completion of Construction
|
9/23/12
|
|
*Dates may be subject to change and such changes will be posted on the ETCOG website.
|