| Project Task |
Date |
| Workshop to discuss the development of a Method of Distribution |
February 13 |
| Public Hearing for Method of Distribution |
February 16 |
| Public Hearing for Method of Distribution |
February 18 |
| Meeting with Counties to discuss the County scoring criteria |
April 15 |
| ORCA grant writing workshop |
April 15 |
| Submission of objective scoring criteria by Counties |
April 24 |
| Public hearing regarding County's criteria |
April 28 |
| Amend MOD & submit to ORCA |
April 29 |
| ORCA approve MOD and application draft |
May 6-8 |
| ETCOG release approved MOD |
May 11 |
| Send out applications to eligible entities |
May 11 |
| Application deadline (4 weeks) |
June 1 |
| ETCOG scoring of applications (2 weeks) |
by June 9 |
| Send project list to Counties |
by June 9 |
| Counties submit applications to ORCA |
by June 30 |